Deliver phase tool · Exclusively for Cogsult clients

DeployPrep 4D sample report

Part of the Cogsult 4D Engagement Framework

Deliver phase, step 3 of 4 in the Cogsult 4D Framework

A certification pass before you hand off to go-live, covering requirements verification, test execution, change control, QA/compliance, and exceptions, so nothing surfaces as a surprise once the system is live.

  • Certify go-live readiness across requirements verification, test execution, change control, QA/compliance, and exceptions
  • See exactly which category is holding back certification, even when the overall score looks strong
  • Every known issue logged with an owner and a remediation plan, not left as a surprise after go-live

Fictional example — Solstice Diagnostics LIMS Go-Live

01Requirements Verification (25%)

Requirements are documented, traced to test cases, and formally signed off before go-live.

02Test Execution (25%)

Test cases exist for every critical requirement, have been run, and either passed or have a documented resolution.

03Change Control Review (20%)

Every scope or requirement change went through a formal, approved change request, with a complete and traceable history.

04QA/Compliance Review (10%)

QA has signed off on the validation package against the applicable regulatory standard, with documentation and SOPs kept current.

05Exceptions (20%)

Every known issue is logged with an owner and a remediation plan, and no blocking exception ships without executive-level acknowledgment.

Certification results

16 of 16 criteria answered.

Requires a 90%+ overall score to certify. Current: 86%.

86/ 100
Conditional — close the gaps below first
Requirements Verification
100 / 100

All requirements are documented, traced, and formally signed off by stakeholders.

Test Execution
75 / 100

Test cases are written and executed; a handful of failures are still working through resolution, and regression/UAT is in its final pass.

Change Control Review
83 / 100

Every change so far has gone through a documented, approved change request; the change history is still being reconciled into a single traceable log.

QA/Compliance Review
83 / 100

QA has signed off on the validation package against the applicable regulatory standard; the SOP update pass is in its final review.

Exceptions
88 / 100

Every known issue is logged with an owner and executive acknowledgment on the one critical item; one exception is still missing a firm target date for its remediation plan.

This assessment reflects the inputs provided and is intended to inform, not replace, professional judgment. Cogsult makes no warranty regarding outcomes and accepts no liability for decisions made based on these results.

Logged Exceptions

Every known issue between now and go-live, with an owner and a remediation plan.

Exception 1
High

PROJ-482

High

Barcode reprint job occasionally duplicates a label when the printer queue is backed up.

J. Alvarez (QA)

2026-09-05

Vendor patch scheduled; add a queue-depth check as an interim workaround.

Exception 2
Medium

PROJ-501

Medium

Result export to the reference lab interface drops the specimen collection timestamp for manually-entered orders.

M. Chen (Integration)

2026-09-12

Mapping fix identified; retest against UAT dataset before sign-off.

This is a fictional project's certification results.

DeployPrep 4D™ is exclusively for Cogsult clients. If your project is heading toward go-live, schedule a consultation to get set up.

Schedule a Consultation

Looking for more free tools, including VendorFit 4D and ProjectPrep 4D?

Browse CogTools